Concrete forming systems and methods
Application Number |
17098396 |
Grant Number |
11559924 |
Status |
In Force |
Filing Date |
2020-11-15 |
First Publication Date |
2021-03-04 |
Grant Date |
2023-01-24 |
Owner |
Goss Construction, Inc. (USA)
|
Inventor |
Goss, Richard A.
|
Abstract
Systems and methods for constructing concrete foundations are provided which allow for rapid and high-precision placement and alignment of anchor bolts across large distances. A frame system is constructed outside of an excavation and then suspended, using supports, over an excavation. The frame system can include a frame having one or more templates for anchor bolts, a form suspended from the frame, and a mat and cage assembly tied to the frame. The frame system can be aligned in proper position and the anchor bolts placed in the frame system before the concrete is placed. In this way, the anchor bolts can be cast in place as the footing is placed.
IPC Classes ?
- B29C 39/10 - Shaping by casting, i.e. introducing the moulding material into a mould or between confining surfaces without significant moulding pressureApparatus therefor for making articles of definite length, i.e. discrete articles incorporating preformed parts or layers, e.g. casting around inserts or for coating articles
- E02D 27/32 - Foundations for special purposes
|
2.
|
Concrete forming systems and methods
Application Number |
16653693 |
Grant Number |
10836080 |
Status |
In Force |
Filing Date |
2019-10-15 |
First Publication Date |
2020-02-06 |
Grant Date |
2020-11-17 |
Owner |
Goss Construction, Inc. (USA)
|
Inventor |
Goss, Richard A.
|
Abstract
Systems and methods for constructing concrete foundations are provided which allow for rapid and high-precision placement and alignment of anchor bolts across large distances. A frame system is constructed outside of an excavation and then suspended, using supports, over an excavation. The frame system can include a frame having one or more templates for anchor bolts, a form suspended from the frame, and a mat and cage assembly tied to the frame. The frame system can be aligned in proper position and the anchor bolts placed in the frame system before the concrete is placed. In this way, the anchor bolts can be cast in place as the footing is placed.
IPC Classes ?
- B29C 39/10 - Shaping by casting, i.e. introducing the moulding material into a mould or between confining surfaces without significant moulding pressureApparatus therefor for making articles of definite length, i.e. discrete articles incorporating preformed parts or layers, e.g. casting around inserts or for coating articles
- E02D 27/32 - Foundations for special purposes
|
3.
|
Concrete forming systems and methods
Application Number |
16147192 |
Grant Number |
10449699 |
Status |
In Force |
Filing Date |
2018-09-28 |
First Publication Date |
2019-01-31 |
Grant Date |
2019-10-22 |
Owner |
Goss Construction, Inc. (USA)
|
Inventor |
Goss, Richard A.
|
Abstract
Systems and methods for constructing concrete foundations are provided which allow for rapid and high-precision placement and alignment of anchor bolts across large distances. A frame system is constructed outside of an excavation and then suspended, using supports, over an excavation. The frame system can include a frame having one or more templates for anchor bolts, a form suspended from the frame, and a mat and cage assembly tied to the frame. The frame system can be aligned in proper position and the anchor bolts placed in the frame system before the concrete is placed. In this way, the anchor bolts can be cast in place as the footing is placed.
IPC Classes ?
- B29C 39/10 - Shaping by casting, i.e. introducing the moulding material into a mould or between confining surfaces without significant moulding pressureApparatus therefor for making articles of definite length, i.e. discrete articles incorporating preformed parts or layers, e.g. casting around inserts or for coating articles
- E02D 27/32 - Foundations for special purposes
|
4.
|
Concrete forming systems and methods
Application Number |
15947601 |
Grant Number |
10112325 |
Status |
In Force |
Filing Date |
2018-04-06 |
First Publication Date |
2018-08-09 |
Grant Date |
2018-10-30 |
Owner |
Goss Construction, Inc. (USA)
|
Inventor |
Goss, Richard A.
|
Abstract
Systems and methods for constructing concrete foundations are provided which allow for rapid and high-precision placement and alignment of anchor bolts across large distances. A frame system is constructed outside of an excavation and then suspended, using supports, over an excavation. The frame system can include a frame having one or more templates for anchor bolts, a form suspended from the frame, and a mat and cage assembly tied to the frame. The frame system can be aligned in proper position and the anchor bolts placed in the frame system before the concrete is placed. In this way, the anchor bolts can be cast in place as the footing is placed.
IPC Classes ?
- B29C 39/10 - Shaping by casting, i.e. introducing the moulding material into a mould or between confining surfaces without significant moulding pressureApparatus therefor for making articles of definite length, i.e. discrete articles incorporating preformed parts or layers, e.g. casting around inserts or for coating articles
- E02D 27/32 - Foundations for special purposes
|
5.
|
Concrete forming systems and methods
Application Number |
14216827 |
Grant Number |
09937643 |
Status |
In Force |
Filing Date |
2014-03-17 |
First Publication Date |
2014-07-17 |
Grant Date |
2018-04-10 |
Owner |
Goss Construction, Inc. (USA)
|
Inventor |
Goss, Richard A.
|
Abstract
Systems and methods for constructing concrete foundations are provided which allow for rapid and high-precision placement and alignment of anchor bolts across large distances. A frame system is constructed outside of an excavation and then suspended, using supports, over an excavation. The frame system can include a frame having one or more templates for anchor bolts, a form suspended from the frame, and a mat and cage assembly tied to the frame. The frame system can be aligned in proper position and the anchor bolts placed in the frame system before the concrete is placed. In this way, the anchor bolts can be cast in place as the footing is placed.
IPC Classes ?
- B29C 39/10 - Shaping by casting, i.e. introducing the moulding material into a mould or between confining surfaces without significant moulding pressureApparatus therefor for making articles of definite length, i.e. discrete articles incorporating preformed parts or layers, e.g. casting around inserts or for coating articles
- E02D 27/32 - Foundations for special purposes
|
6.
|
CONCRETE FORMING SYSTEMS AND METHODS
Application Number |
US2012055628 |
Publication Number |
2013/040495 |
Status |
In Force |
Filing Date |
2012-09-14 |
Publication Date |
2013-03-21 |
Owner |
GOSS CONSTRUCTION, INC. (USA)
|
Inventor |
Goss, Richard, A.
|
Abstract
Systems and methods for constructing concrete foundations are provided which allow for rapid and high-precision placement and alignment of anchor bolts across large distances. A frame system is constructed outside of an excavation and then suspended, using supports, over an excavation. The frame system can include a frame having one or more templates for anchor bolts, a form suspended from the frame, and a mat and cage assembly tied to the frame. The frame system can be aligned in proper position and the anchor bolts placed in the frame system before the concrete is placed. In this way, the anchor bolts can be cast in place as the footing is placed.
IPC Classes ?
- E02D 27/42 - Foundations for poles, masts, or chimneys
- E02D 27/32 - Foundations for special purposes
|
7.
|
CONCRETE FORMING SYSTEMS AND METHODS
Document Number |
02884519 |
Status |
In Force |
Filing Date |
2012-09-14 |
Grant Date |
2017-02-21 |
Owner |
GOSS CONSTRUCTION, INC. (USA)
|
Inventor |
Goss, Richard A.
|
Abstract
Systems and methods for constructing concrete foundations are provided which allow for rapid and high-precision placement and alignment of anchor bolts across large distances. A frame system is constructed outside of an excavation and then suspended, using supports, over an excavation. The frame system can include a frame having one or more templates for anchor bolts, a form suspended from the frame, and a mat and cage assembly tied to the frame. The frame system can be aligned in proper position and the anchor bolts placed in the frame system before the concrete is placed. In this way, the anchor bolts can be cast in place as the footing is placed.
IPC Classes ?
- E02D 27/32 - Foundations for special purposes
- E02D 27/42 - Foundations for poles, masts, or chimneys
|
|